Key Facts
- Demolition of former hospital occupying an approx 20Ha site including asbestos removal and limited remediation
- Operational medical facilities adjacent and local community to all boundaries required on going liason and air monitoring was implemented for the neighbours reassurance.
- The site participated in the Considerate Constructors scheme and achieved Performance beyond compliance with a score of 43 and a subsequent National Gold award
- The site produced approx 170,000 tonnes of crushed material for reuse in the future redevelopment
- The site required extensive tree protection and ecology works
Location: Bristol
Duration: 12 months