Demolition case study - Maidenhead town centre

Date: 19/09/2017

Key Facts

  • Demolition of 6 storey council office building and formation of temporary car park
  • Town centre location next to the river Thames
  • Existing ground floor slab and car park area repaired. Boundary to the site secured on three sides with a 2.0 m high steel mesh fence as the boundary to the river side elevation is secured with the existing fencing.
  • Asbestos based materials removed and disposed of to suitably licensed waste disposal sites.



Location: Maidenhead Town Centre
Duration: 5 months
 