Mill Chase Academy, Bordon

The project necessitated the demolition of 15 different structures and the form of construction varied from a traditional brick build to steel or reinforced concrete frame with the onsite sports hall and leisure centre being portal framed with composite panels housing a gym and swimming pool.

The project scope required all buildings to be demolished including removal of the 3g multi use sports (MUGA) pitch that was to the rear of the site.

One of the main constraints of the project was the coordination required in maintaining service to the leisure centre throughout the first phase of works as it was a contractual requirement to remain open due to an outstanding client lease agreement.

The second phase relying on the decant of the leisure and utility disconnections being delivered quickly which enabled us to complete demolition and removal of all substructures.

Summary of the Scope of Works:

Sustainably remove 170 tonne 3g MUGA pitch
Retention of existing live UKPN substation
Protection and retention of live underground gas main
550m of tree protection
Extensive removal of asbestos containing materials
Demolition of 15 nr structures of varying construction types
6,000m3 materials sustainably recycled
Interactions and Communications with local community groups