Case Studies / Nash Court, Oxford

Nash Court, Oxford

R. Collard Limited successfully completed the full demolition of seven two-storey office blocks, preparing the site for its future development.

The project included essential enabling works such as hoarding installation and tree protection, followed by a comprehensive soft strip and asbestos removal process.

The team carried out full demolition, including the removal of slabs and foundations, with proof digging up to 2.5m to eliminate any underground obstructions. Additionally, foul and storm drainage systems were capped for reuse in the upcoming construction phase.

To maximise sustainability, hard-core materials were crushed to 6F2, and concrete from slabs and arisings was processed into Type 1 material for on-site reuse.

This efficient and environmentally responsible approach ensured the site was fully prepared for the next phase of development.

Summary of the Scope of Works:

Enabling works (Hoarding and Tree protection).
Soft strip.
Asbestos removal.
Full Demolition.
Capping of Foul and Storm drainage that feed into the public lines (To be reused for the new build).
Removal of slab and foundations.
Proof digging (Up to 2.5m depth to remove any obstructions in the ground ready for piling by the next Contractors).
Crushing of Hard-core to 6f2 and Concrete from slab and arisings to type 1 material for reuse on site.