Other Relevant Case Studies

R Collard Divider
Case Studies / Fairway Avenue, Greenford

Fairway Avenue, Greenford

This was a ground remediation project to remove hazardous soils from site to a specialist tip, in some areas down to a depth of 2.5m.

It required the transport and removal of up to 40 loads per day of material off site.

In tandem with the muck away operations, we were required to import suitable material in order to re-establish the site back to the correct level. Utilising our in house substantial vehicle fleet, we were able to minimise vehicle movements to site.

Throughout the process, Amiante STR, our specialist in house hazardous waste management business, maintained a watching brief to further enhance best working practices and ensure statutory compliance was of the highest possible standards.

A further element to the project throughout the excavation process entailed the breakup and crushing of concrete obstructions found. This material was re used on site, further minimising vehicle movements.

Summary of the Scope of Works:

Excavation and safe disposal of contaminated soil
Import of suitable fill
Exposing concrete obstructions
Crushing concrete material and provide a working platform for future works

Related Case Studies

Sign up to our newsletter

Keep up to date with everything Collard.